by: Leonardo Corbucci 13 Agosto 2020 12:39

Module srl: work progress

During the week of August 15th, the installation work of the MODULO364 photovoltaic system continues unabated.

According to the planning shared with our suppliers, the activities could end at the end of September 2 months in advance of the contract and with the plant going into operation as early as next October.

In the images you are seeing, almost all the aluminum support structures are already fixed on the industrial roofs, the photovoltaic modules will begin to be mounted on Monday 24 August. In these days all the inverters and electrical panels have also been positioned.

In partnership with Ener2Crowd.