by: Leonardo Corbucci 22 Novembre 2018 17:14
SCATOLIFICIO SAICO SRL – Work progress
Work continues on schedule for the umbrian customer, Scatolificio Saico. In recent months all the permits have been obtained for the important logistic expansion of the Col di Pozzo (PG) plant.
In these days the foundations will be realized, while at the planning level the prefabricated structure should be completed by the middle of december.